The J.H. Campbell coal plant was supposed to close in May 2025. It is still working.

The plant has now received seven emergency orders.

At this point the emergency has dental coverage.

A federal appeals court ruled that the Energy Department overstepped when it issued the first order. The court said the government used a reliability study out of context and that unspecified long-term risks did not create an emergency.

The Energy Department issued another emergency order.

Good. The legal system has submitted its comment card.

The new order keeps the plant open through February 12, 2027. It says the regional grid remains at elevated risk.

The Daily Heckler: five or six selected stories.
Political satire for your morning inbox.

Elevated risk means the grid has adequate resources, except extreme weather could create a shortfall.

So the emergency is that something might happen later.

That is not an emergency. That is a calendar.

Consumers Energy has said it intends to recover the costs of keeping the plant open. Those costs could fall on ratepayers across ten Midwestern states.

The plant was ready to retire. The court agreed. The bill will be sent to people who were not consulted.

Everybody in this process gets a choice except the customer and the coal plant.

The plant filed for retirement.

The government marked it absent.